Step 3: Execution of the preparatory work and dispatch of all necessary documents to Creos

Preparatory work for the electrical installation

You must ensure that your electrician has correctly completed his preparatory work for the connection of your installation to the Creos electricity grid.

Send the documents back to Creos

Standard-mode: The order and the contracts will be sent to our address signed by you. The completion report signed by your electrician must also be sent to our address. Once we have all these documents, Creos will email you to arrange an appointment to check the installation.

Fast track-mode: All work must be completed for the first fixed date and all documents necessary for the commissioning of the photovoltaic system must be available to us at least 3 days before this date. If the installation complies with the applicable TAB regulations and standards on the first date, the second date for the commissioning of the PV system can be met. Otherwise, the second fixed date will be cancelled and your request will be processed in standard-mode.

    • The preparatory work for the electrical installation must be carried out by an electrician approved in the Grand Duchy of Luxembourg.
    • The end of work notification and contract for the supply of electrical power from production installations based on power sources are essential elements; without them your application will not be processed.

    Specific terms and conditions for existing independent power production equipment that will be operated in self-consumption mode:

    • Once the electrician has made changes in the meter board, the independent electrical power production equipment cannot be activated until the Creos operators transfer the meter.
    • The Creos operators must put every independent production equipment into service individually when installing the meter.