Step 4: Making an appointment to approve the preparatory work

This step is not required in fast track-mode.

The following documents are required to verify the installation:

  • The order signed by the subscriber or his authorized representative.
  • Connection, use and energy buy-back contracts signed by the plant operator.
  • The completion report signed by the electrician.

Once we have all these documents, Creos will ask you to make an appointment to review the installation.

    Specific terms and conditions for existing independent power production equipment that will be operated in self-consumption mode:

    It is recommended that the meter board transformation works by the electrician and the meter transfer by Creos operators be carried out on the same day so as to avoid downtime of the independent power production equipment.