The hydrogen routes of the future are taking shape, and Luxembourg intends to be part of them. Through the HY4Link project, the country aims to diversify its energy supplies and reduce its dependence on fossil fuels. From industry to heavy transport, project manager Jean-François Schneiders explores the opportunities and challenges of this emerging European network.

What specific problem is HY4Link intended to solve in Luxembourg?

Our goal is to help achieve climate neutrality by 2050. Today, some industrial sectors use natural gas in their production processes. Renewable or low-carbon hydrogen offers an alternative, particularly for activities requiring high temperatures, such as steelmaking. There is also an economic dimension: supporting industrial companies through the transition while helping to keep their operations in Luxembourg and Europe.

What uses do you envisage beyond industry?

There could be applications in heavy transport, particularly trucks. For buses, we see more specific uses. We are also exploring the potential of certain district heating networks. However, we do not envisage systematically replacing natural gas with hydrogen in individual boilers. The cost would be too high, and other solutions are available.

Why develop hydrogen when electrification is already progressing?

The two are complementary. Electrification and the development of renewable energy will continue, but there will still be specific needs that hydrogen can meet. It could also play a role in energy storage. Surplus solar or wind electricity could be used to produce hydrogen through electrolysis, a process that splits water into hydrogen and oxygen. Energy would thus be stored as hydrogen for longer periods than batteries generally cover.

Where will the hydrogen transported through HY4Link come from?

We expect most of it to be imported. Production capacity in Luxembourg is limited. Two initial local electrolyser projects are receiving public support. They are important for getting the market started, but they will not be sufficient to provide the volumes needed to decarbonise industry. HY4Link aims to give Luxembourg access to two major supply routes: the North Sea, with its wind energy potential and import infrastructure, and the Iberian Peninsula, where solar and wind resources could enable more competitive production.

The network is scheduled to be rolled out in two stages: a connection to France by around 2032, followed in 2034–2035 by a connection to Belgium and the construction of a pipeline crossing Luxembourg towards France and Germany. Why start with France?

Luxembourg’s main industrial hubs are in the south of the country. The French connection, which includes links between Frisange, Thionville, Bouzonville and the Nancy region, therefore addresses their needs first. It is also intended to connect us to mosaHYc, the Franco-German network serving, among others, the Saarland steel industry, and to HY-FEN, which will provide access to hydrogen transported from southern Europe. Luxembourg will thus benefit from larger volumes of hydrogen and gradually become integrated into the European network.

How much investment does the first phase represent, and how will it be financed?

The first phase in Luxembourg represents an estimated investment of €100 million. We are counting on national support and are working with our partners to explore European funding opportunities. HY4Link’s status as a European Project of Common Interest facilitates access to EU funding schemes.

Why seek public guarantees in addition to investment aid?

If demand does not develop as expected, the network could be underused. This risk partly depends on economic and political factors beyond our control as a network operator. The government is working on a guarantee mechanism to share this risk with us and our shareholders. Developing the network in two phases also helps reduce risk: first by serving clearly identified industrial hubs, then by developing transit activities that depend more heavily on the regional market.

Where will the pipelines run during the first phase, and why not reuse natural gas pipelines?

The planned route for the first phase passes through twelve municipalities in the south of the country. It largely follows the A13 motorway and also runs along roads. The route still needs to undergo an environmental impact assessment and permitting procedures and may be adjusted as a result.

We plan to build new steel pipelines. Some natural gas pipelines could be repurposed following appropriate checks, but Luxembourg does not have the spare capacity to do this while continuing to supply its natural gas customers. A separate network is therefore necessary.

What specific precautions are required when transporting hydrogen?

Hydrogen requires appropriate design, testing, inspections and regular maintenance. We draw on German technical standards and accredited bodies. Our teams will also need training in hydrogen-specific requirements before commissioning, particularly for operation and maintenance.

Despite the uncertainties, are you convinced that Luxembourg should move forward with this project?

Yes, without a doubt. Even if it is difficult to predict whether the market will take off, we need to act. Neighbouring countries are developing their hydrogen transport infrastructure, and Luxembourg must be able to participate in this development to retain its industry, diversify its sources of supply and reduce its dependence on fossil fuels.

Interview by Stéphane Etienne