6 steps to your gas connection
Step 3: Carrying out the connection work
The civil engineering work
You are responsible for the preparatory work prior the intervention by Creos, i.e. digging the trench between the gas grid and the building's connection point. This civil engineering work must be carried out according to our instructions and as stipulated in Creos's connection conditions. All the authorisations necessary for work on the public road network must be available before the start of the work.
Connection work done by Creos
Creos will make the connection to the natural gas grid on the date agreed with your contractor.
Paying for the connection
Once the connection has been made, you will receive an invoice by mail, corresponding to the work carried out.
- You must be assisted by a contractor who is Alugaz-certified to carry out the civil engineering work.
- For safety reasons the connection may be made only once the civil engineering work has been completed and is subject to the building being closed (roof, doors, windows).
- The trench must be ready on the date agreed for Creos to hook you up to the gas network.
- If Creos carries out the work after the period of validity of the order, the work will be invoiced at the current price.