6 steps to your power connection
Step 5: Checking the preparatory work by Creos
Creos approves and validates the electrical installation preparatory work. Once the preparatory work has been validated, the Creos agent will make an appointment to carry out the agreed work.
Should approval of the preparatory work not be possible, a report report will be sent to you with the request to have the preparatory work corrected and to make a further appointment (see under Step 4).
- It is recommended that your electrician is present during the visit by the Creos agent in charge.
- Only one visit by this agent to check the preparatory work is included in the Creos connection price. Any additional visit will be invoiced at the current price.
Specific terms and conditions for existing independent power production equipment that will be operated in self-production mode:
To keep the downtime of the independent power production equipment to the minimum, the transfer or the installation of the meter will be carried out during the check session.
The electrician must be present during this session.